John and Kathleen’s Santa Cruz ADU in its Early Stages

I live in Santa Cruz and have a decently large lot, and we want to build an accessory dwelling unit (ADU) with a garage in our backyard for my father-in-law,” John inquired New Avenue at the end of November 2012. We visited John and his wife, Kathleen, shortly thereafter to check out what their options could be. After some zoning research, we determined that, with a lot size between 5,000 to 7,000 sq ft, the couple would be allowed to build their Santa Cruz ADU with:

  • A floor area of up to 500 sq ft, measured from exterior walls, not including a first floor garage.

  • Height of 22’ for a two-story unit.

  • 5’ side setback for two-story unit, 3’ for a one-story unit.

  • 10’ rear setback with AUP, 20’ without an AUP. (An AUP, or administrative use permit, may be required by a planning/development department to review and assure that construction or property use are consistent with zoning regulations. It adds time and costs to the project but can afford leniencies for the building.)

  • Required fire sprinkler system.

  • Design similar to the primary residence.

Santa Cruz is a beautiful and progressive city by the ocean but buying and renting a house is very expensive. In the early 2000s, a city committee looked to ADUs as a solution to address the shortage of affordable housing. While they housing code already permitted them, it wasn’t easy for homeowners to develop them. The city introduced ADU ordinances to encourage homeowners to build ADUs as well as some methodical restrictions on how they could be constructed or used. This move has been well received by Santa Cruz communities and homeowners alike.

We drew up a handful of site plans for John and Kathleen and took note that they wanted some room in the yard for their young son. Upon deciding where and how the ADU will be located in the backyard, we came up with a rough schematic sketch of the unit. The family is big on bikes, so room for them is an important part of the layout.

0325JK-7.png

This early design process underwent several iterations before a floor plan was agreed on. Here are some of the schemes. They are labeled A-E on the lower right.

Scheme A

A.png
A2.png
A3.png
A4.png

Scheme B

B.png
B1.png
B2.png
B3.png

Scheme C

C.png
C1.png

Scheme D

D.png
D1.png

Scheme E

E.png
E1.png
E2.png
E3.png

After some back-and-forth with John and Kathleen, we arrived at scheme E for the final design.

To get your questions answered and talk about your project, schedule a free call. We’ll discuss the possibilities for your home, our process, budgets, timelines, and permits.